SCHEDULE AND BUDGET FOR COMPLETION OF HIGH SPEED SPECIAL PROCESSING UNIT
14 May 1973
Design of the Processor is complete, including logic drawings,
printed circuit and wirewrap cards. Assuming that certain parts with
a total value of $67,500 are donated by Digital Equipment Corporation
as expected, the project can be finished in about one year for the
following cost.
Personnel Costs
Salaries - 3 design engineers for 12 months,
plus 1 programmer for 8 months,
plus 1 programmer for 3 months $57,000
Staff benefits (17%) 9,690
Travel - 4 East coast @$500, 10 West coast @ $100 3,000
Miscellaneous direct costs 3,000
Indirect costs (47% of above) 34,164
Personnel Subtotal 106,854
Parts and Services
Integrated circuits
9000 TI and other donated
400 AMS memory chips 31,000
31,000
Printed circuit cards
Artwork for 24 cards @ $400 9,600
Fabricate 163 cards of 24 types 39,600
Stuff & solder 110 @ $20,
25 @ $200 7,200
56,400
Wirewrap cards
Artwork 600
Card fabrication 65 @ $100 6,500
Sockets, capacitors 55 @ $135 7,425
Stuff and solder 55 @ 92 5,060
Wiring 55 @ $146 8,030
27,615
Backpanel
2 KI-10 bays with sockets donated
10,000 single wires @ .10 donated
26,000 twisted pair @ .25 donated
0
Power supplies
cabinet 800
500 Amperes @ $10 per Amp. 5,000
5,800
Cooling equipment 1,000
Card tester 3,000
Parts and services subtotal 124,815
Contingencies 10,000
Project total 241,669
SCHEDULE
Week
1-8 Order ICs (from DEC and AMS), backpanel (DEC), PC cards & bases for
wirewrap cards (Vostron), power supplies (Lambda), card tester
(SOTTA).
2-14 Assemble card tester, debug tester and test programs.
Write console computer software. Monitor fabrication processes.
10-16 Delivery of wirewrap and PC cards.
12-20 Delivery of ICs.
20 Delivery of backpanel and power supplies.
15-26 Wirewrap card wrapping, stuffing, and testing (1 card per day).
15-29 PC card stuffing, soldering, and testing (2 cards/day).
24-30 Final assembly and preliminary debugging.
30-52 Processor debugging, bringing up new system.
NOTES
1. Delivery of integrated circuits, etc. are based on quotes
received in January. These times may be different now.
2. When informal approval is received, some long lead time items
could be ordered with donated funds.